A framework agreement is an agreement between one or more public buyers and one or more suppliers that sets the terms, particularly price and, where appropriate, quantity, for contracts to be awarded over a given period. Winning a place on a framework is not winning work: the contracts come later, under its terms.
The EU rules are in Article 33 of Directive 2014/24/EU, and for utilities in Article 51 of Directive 2014/25/EU.
How long can a framework agreement last?
Four years under the general directive and eight under the utilities directive, except in exceptional cases duly justified, in particular by the framework's subject matter.
How is work awarded under a framework?
- One supplier: contracts follow the framework's terms. The buyer may ask the supplier in writing to supplement its tender as necessary.
- Several suppliers, all terms set: the buyer awards directly, choosing the supplier by objective conditions set out in the procurement documents.
- Several suppliers, terms still open: the buyer reopens competition, often called a mini-competition. It consults in writing the suppliers able to do the work, sets a time limit, and awards to the best tender against the framework's award criteria.
A framework may combine both methods if its documents say when each applies. Only the buyers identified in the call for competition may use it, and contracts under it may not substantially change its terms.
What does a framework's value mean?
The maximum value, net of VAT, of all the contracts planned over its whole term (how buyers count a contract's value): a ceiling, not a promise. A minimum turnover requirement may not exceed twice the contract value unless duly justified; for a framework, that limit is worked out from the largest contracts expected to run at the same time.
The notice says whether a tender sets up a framework (how to read a TED notice), and a framework can be split into lots. Browse the tender directory.
Questions and answers
How long can a framework last in the UK?
The Procurement Act 2023 sets four years, and eight for defence and security or utilities frameworks.
Does a place on a framework guarantee work?
No. The work comes through direct awards or mini-competitions (go or no-go questions).
What is a mini-competition?
A reopening of competition among the suppliers on a framework when not all terms are fixed. The best tender against the framework's award criteria wins.
- Directive 2014/24/EU on public procurement: Article 5 (estimated value), Article 33 (framework agreements) and Article 58 (selection criteria, minimum yearly turnover), checked 31 October 2026: https://eur-lex.europa.eu/eli/dir/2014/24/oj
- Directive 2014/25/EU on procurement by entities operating in the water, energy, transport and postal services sectors: Article 51 (framework agreements), checked 31 October 2026: https://eur-lex.europa.eu/eli/dir/2014/25/oj
- Procurement Act 2023, section 47 (frameworks: maximum term), checked 31 October 2026: https://www.legislation.gov.uk/ukpga/2023/54/section/47