A lot is a separate part of a tender that is bid for and awarded on its own. Under Directive 2014/24/EU the buyer decides the size and subject matter of each lot, and if it does not divide a contract, it must give the main reasons.

Lots may be drawn by region, by type of work or by stage, so a lot may fit your company when the whole contract does not.

Can I bid for more than one lot?

The contract notice says whether tenders may cover one lot, several or all of them. The buyer may also cap the number of lots one tenderer can win, if the notice states the cap, and the documents then say how it chooses which lots a tenderer gets. Some countries let buyers award several lots together, where the notice reserves that possibility.

How do lots change the requirements?

Selection criteria apply lot by lot. A minimum turnover requirement may not exceed twice the estimated contract value, except in duly justified cases, and it is set for each lot, or for groups of lots won together and performed at the same time. Where selection criteria differ between lots, you fill in an ESPD for each lot, or for each group of lots with the same criteria.

Do lots change the EU threshold?

No. The buyer adds up all the lots, and if the total reaches the threshold, the directive applies to every lot. A buyer may still award small lots outside it: under €80,000 for supplies or services, or under €1 million for works, as long as those lots together do not exceed 20% of the value of all the lots (EU thresholds for 2026 and 2027).

Each lot's title and value are in the notice (how to read a TED notice). Browse the tender directory.

Questions and answers

Must UK buyers use lots?

Under the Procurement Act 2023, buyers must consider lots before publishing a tender notice, and give reasons where lots would be appropriate but are not used.

Is the turnover requirement set for the whole contract or for each lot?

For each lot, at no more than twice its estimated value unless duly justified.

Can a framework agreement have lots?

Yes, so you may win a place on some lots of a framework but not others.

Sources
  1. Directive 2014/24/EU on public procurement: Article 5 (estimated value of lots), Article 33 (lots of a framework agreement), Article 46 (division of contracts into lots) and Article 58 (selection criteria, minimum yearly turnover), checked 31 October 2026: https://eur-lex.europa.eu/eli/dir/2014/24/oj
  2. Commission Implementing Regulation (EU) 2016/7 establishing the standard form for the European Single Procurement Document: Annex 1 (instructions, an ESPD for each lot), checked 31 October 2026: https://eur-lex.europa.eu/eli/reg_impl/2016/7/oj
  3. Procurement Act 2023, section 18 (duty to consider lots), checked 31 October 2026: https://www.legislation.gov.uk/ukpga/2023/54/section/18

The Herald, free each working morning. One tender analysed in depth, then big tickets, quick wins, deadlines and awards. Engineering and Water first.

Get the Herald

Read next