The UK Procurement Act 2023 for suppliers: what changed

What the Procurement Act 2023 changed for suppliers: the procedures, the most advantageous tender, standstill, exclusions, debarment, KPIs and 30-day payment.

The Procurement Act 2023 replaced the Public Contracts Regulations 2015 on 24 February 2025 for new procurements by UK government bodies and by public buyers in England, Wales and Northern Ireland. For suppliers, the main changes are two competitive procedures in place of five, contracts awarded to the "most advantageous tender", a standstill period of eight working days, an assessment summary for every tender that was assessed, a published debarment list, and published key performance indicators for contracts above £5 million.

Procurements started under the 2015 Regulations before that date stay under them, and so do the contracts they produce, until those contracts end. Devolved Scottish authorities keep their own rules. Where the new notices are published is covered in where to find public tenders in the UK.

What changed, at a glance?

TopicPublic Contracts Regulations 2015Procurement Act 2023
Competitive proceduresOpen, restricted, competitive procedure with negotiation, competitive dialogue, innovation partnershipOpen procedure, or a competitive flexible procedure the buyer designs
Who winsThe most economically advantageous tenderThe most advantageous tender
Standstill periodUntil midnight at the end of the 10th day after the award decision is sent electronicallyEight working days from the day the contract award notice is published
Framework termUp to 4 years, save in exceptional casesUp to 4 years; 8 for defence and security or utilities frameworks; open frameworks up to 8 years
Flexible supplier listsDynamic purchasing systemsDynamic markets

How do the new procedures work?

There are two. The open procedure is a single stage that any supplier may enter. The competitive flexible procedure is any other competitive procedure the buyer considers appropriate: it may run several rounds, limit the number of suppliers at each stage, exclude suppliers that fail the conditions of participation or an intermediate assessment of tenders, and refine the award criteria as it goes. It may not let in a supplier that did not tender in the first round or was excluded in an earlier one.

Either way, the procedure must be proportionate to the contract's nature, complexity and cost, and buyers must consider whether the barriers small and medium-sized enterprises face can be removed or reduced. Under the competitive flexible procedure each buyer sets its own stages, and the tender notice and documents describe them, so read both before planning the bid. The minimum time limits are in the procedures and their time limits.

What is the "most advantageous tender"?

The tender that the buyer considers satisfies its requirements and best satisfies the award criteria, assessed by the methodology and relative importance of the criteria set out in advance. The criteria must relate to the subject of the contract, be clear, measurable, specific and proportionate, and may cover price and other costs, how and when the work is delivered, and the staff's qualifications and experience where these make a material difference to quality.

Three points matter for a bid:

  • Pass or fail criteria. The buyer must say whether failing one or more criteria would disqualify a tender. Find those criteria first.
  • Weighting. With more than one criterion, the buyer must show their relative importance: as percentages, as a ranking, or described in another way.
  • Procedural requirements. A buyer may disregard a tender that breaches a procedural requirement in the tender notice or documents, including a requirement to provide information. A missing document can be enough to have a tender set aside.

A buyer may also disregard a tender whose price it considers abnormally low, but only after telling the supplier and giving it a reasonable opportunity to show it can perform the contract for that price.

What do you learn if you lose?

Before it publishes the contract award notice, the buyer must give every supplier whose tender was assessed, and not disregarded, an assessment summary: information about how its own tender was assessed and, if different, how the most advantageous tender was assessed. Read it before asking the buyer for more.

The buyer may then not sign the contract until the mandatory standstill period ends: eight working days beginning with the day the contract award notice is published. Call-offs from frameworks, contracts awarded through a dynamic market, light touch contracts and urgent direct awards, among others, have none; a buyer may set a voluntary one, of at least eight working days. Once it ends, the contract can be signed, so note the date when the notice appears.

How are suppliers excluded now?

The Act separates excluded suppliers, to which a mandatory exclusion ground applies, from excludable ones, to which a discretionary ground applies. The mandatory grounds are in Schedule 6 of the Act and the discretionary ones, such as labour market misconduct, in Schedule 7. Either applies when the ground applies to the supplier or an associated person and the circumstances are continuing or likely to occur again.

That is where evidence counts: the buyer may consider whether the supplier took the circumstances seriously, for example by paying compensation, what it has done to prevent a repeat, such as changing staff or management or putting procedures and training in place, its commitments to further steps, and the time that has passed. The buyer must let the supplier make representations and provide evidence before deciding, so if a past problem might count against you, have that evidence ready before you bid.

There is also a debarment list, published by a Minister of the Crown. After an investigation, a supplier may be entered on it with the exclusion ground and the date it is expected to stop applying, but only eight working days after being told. A supplier on the list because of a mandatory ground is an excluded supplier: buyers do not have to establish the ground themselves.

What changes once you win?

  • Key performance indicators. Before signing a contract worth more than £5 million, the buyer must set at least three, unless performance could not appropriately be assessed that way, and publish them. Frameworks, concessions, light touch contracts and contracts awarded by private utilities are exempt.
  • Published performance. At least once a year, and when the contract ends, the buyer must assess and publish performance against those indicators. If a breach leads to termination, damages or a settlement, or a supplier fails to improve poor performance after a proper opportunity, the buyer must publish that within 30 days.
  • Payment in 30 days. Every public contract is treated as requiring payment within 30 days of the buyer receiving a valid invoice, or the day payment falls due under it if later, unless the buyer disputes the invoice or considers it invalid. The same term is implied into the sub-contracts that perform a public contract, and a term that overrides it has no effect. Concessions, contracts awarded by private utilities and contracts awarded by schools are exempt.

What happened to frameworks and dynamic purchasing systems?

A framework may run for up to four years, or eight for a defence and security or utilities framework, unless the buyer gives its reasons for a longer term in the notice. New is the open framework: a scheme of successive frameworks on substantially the same terms, reopened at least once in the first three years and then at least once every five years from the second award, ending within eight years. If you miss the first award, watch for the next.

Dynamic markets take the place of dynamic purchasing systems. A buyer sets one up, announced by a dynamic market notice, and may then limit a competitive flexible procedure to its members; it must first consider any application to join from a supplier that has asked to take part or tendered.

What should suppliers do now?

  1. Register on Find a Tender and keep your core supplier information up to date (the registration steps).
  2. For each tender, find the assessment methodology, the pass or fail criteria and the weighting before deciding to bid (the go or no-go questions).
  3. Keep evidence of how past problems were put right, in case an exclusion ground is raised.
  4. Watch for dynamic market notices and open framework reopenings in your field.

The UK's open tenders are in the tender directory, updated every morning.

Questions and answers

When did the Procurement Act 2023 come into force?

On 24 February 2025. Procurements started under the Public Contracts Regulations 2015 before then continue under those regulations, and their contracts are managed under them until they end.

Does the Procurement Act 2023 apply in Scotland?

Not to devolved Scottish authorities, which remain under the Public Contracts (Scotland) Regulations 2015 and Scotland's other procurement rules. It does apply to UK government bodies, and to public buyers in Wales and Northern Ireland.

How long is the standstill period under the Procurement Act?

Eight working days, beginning with the day the contract award notice is published. Under the 2015 Regulations it ended at midnight at the end of the 10th day after the decision was sent electronically.

What replaced MEAT?

The most advantageous tender: the one the buyer considers satisfies its requirements and best satisfies the award criteria, assessed by the methodology and weighting set in advance.

Sources
  1. Procurement Act 2023: section 12 (objectives, including small and medium-sized enterprises), section 19 (award to the most advantageous tender; in force on 24 February 2025 by S.I. 2024/716), section 20 (open and competitive flexible procedures), section 23 (award criteria) and sections 34, 35 and 39 (dynamic markets), checked 11 November 2026: https://www.legislation.gov.uk/ukpga/2023/54/section/19
  2. Procurement Act 2023: section 47 (frameworks: maximum term) and section 49 (open frameworks), checked 11 November 2026: https://www.legislation.gov.uk/ukpga/2023/54/section/47
  3. Procurement Act 2023: section 50 (contract award notices and assessment summaries), section 51 (standstill periods) and section 52 (key performance indicators), checked 11 November 2026: https://www.legislation.gov.uk/ukpga/2023/54/section/51
  4. Procurement Act 2023: section 57 (excluded and excludable suppliers), section 58 (considering whether a supplier is excluded or excludable), section 62 (debarment list) and Schedule 7 (discretionary exclusion grounds), checked 11 November 2026: https://www.legislation.gov.uk/ukpga/2023/54/section/57
  5. Procurement Act 2023: section 68 (implied payment terms), section 71 (assessment of contract performance) and section 73 (implied payment terms in sub-contracts), checked 11 November 2026: https://www.legislation.gov.uk/ukpga/2023/54/section/68
  6. The Public Contracts Regulations 2015, as they stood on 23 February 2025: regulation 26 (choice of procedures), regulation 33 (framework agreements), regulation 34 (dynamic purchasing systems), regulation 67 (award criteria, the most economically advantageous tender) and regulation 87 (standstill period), checked 11 November 2026: https://www.legislation.gov.uk/uksi/2015/102/contents/2025-02-23
  7. The Procurement Regulations 2024, regulation 6 (sharing core supplier information through the central digital platform), checked 11 November 2026: https://www.legislation.gov.uk/uksi/2024/692/regulation/6
  8. GOV.UK, Procurement Act 2023 guidance: transitional and saving arrangements, checked 11 November 2026: https://www.gov.uk/government/publications/procurement-act-2023-guidance-documents-plan-phase/guidance-transitional-and-saving-arrangements-html
  9. Scottish Government, Public procurement: cross-border co-operation within the UK, SPPN 5/2026 (devolved Scottish authorities remain under the Public Contracts (Scotland) Regulations 2015), checked 11 November 2026: https://www.gov.scot/publications/public-procurement-cross-border-co-operation-within-the-uk-sppn-5-2026/