Open, restricted or negotiated: the EU procedures and their minimum time limits
The EU procurement procedures, the minimum time limits for each, when a buyer may shorten them, and when it must give you more time.
Under Directive 2014/24/EU, EU public buyers award contracts through one of five procedures with a call for competition: open, restricted, competitive procedure with negotiation, competitive dialogue or innovation partnership, and in a few exceptional cases they negotiate without publishing a notice. The minimum time for tenders is 35 days in an open procedure; in the other four it is 30 days for requests to participate, followed in a restricted or negotiated procedure by 30 days for tenders.
These minimums apply to contracts at or above the EU thresholds, and buyers may shorten them only in defined cases.
Which procedures can EU public buyers use?
Article 26 of the directive sets the choice. Every EU country must let its buyers use the open procedure, the restricted procedure and the innovation partnership; the other two are for defined cases.
- Open procedure: one stage. Any interested company submits a full tender, with the selection information the buyer asks for.
- Restricted procedure: two stages. Any company may request to participate; only those the buyer invites submit tenders, and the buyer may limit their number.
- Competitive procedure with negotiation: invited companies submit initial tenders, which the buyer negotiates to improve. The minimum requirements and the award criteria are not negotiable, and the buyer may award without negotiating if it reserved the right to.
- Competitive dialogue: the buyer discusses its needs with the selected participants until it has identified one or more solutions, then asks for final tenders. The award is on the best price-quality ratio only.
- Innovation partnership: for a need that nothing already on the market can meet. The buyer works with one or several partners in phases, from research to buying the result.
The competitive procedure with negotiation and the competitive dialogue need a reason: a need that ready-made solutions cannot meet without adaptation, design or innovation, that cannot be specified precisely enough by reference to a standard, or that cannot be awarded without negotiation because of its complexity or risks. They may also follow an open or restricted procedure that drew only irregular or unacceptable tenders.
What are the minimum time limits for each procedure?
The figures are in Articles 27 to 31. Requests to participate, and tenders in an open procedure, are counted from the day the contract notice is sent; tenders in a two-stage procedure from the day the invitation to tender is sent. All figures are in days.
| Procedure | Stage | Standard | Electronic tenders | After a PIN | Urgency |
|---|---|---|---|---|---|
| Open | Tenders | 35 | 30 | 15 | 15 |
| Restricted | Requests to participate | 30 | – | – | 15 |
| Restricted | Tenders | 30 | 25 | 10 | 10 |
| Competitive procedure with negotiation | Requests to participate | 30 | – | – | 15 |
| Competitive procedure with negotiation | Initial tenders | 30 | 25 | 10 | 10 |
| Competitive dialogue | Requests to participate | 30 | – | – | – |
| Innovation partnership | Requests to participate | 30 | – | – | – |
Where a prior information notice was itself the call for competition, requests to participate are counted from the day the invitation to confirm interest is sent. The directive sets no minimum for tenders in the competitive dialogue or the innovation partnership.
When can a buyer shorten the time limits?
- After a prior information notice (PIN). If the buyer sent a PIN for publication between 35 days and 12 months before the contract notice, with the information a contract notice needs as far as it was available, and did not use it as the call for competition, the time for tenders may be cut to 15 days in an open procedure and 10 in a restricted or competitive procedure with negotiation (what a prior information notice is).
- Electronic tenders. A buyer that accepts tenders submitted electronically may take five days off the time for tenders. Electronic submission has been the rule since 18 October 2018 at the latest, with a few exceptions, so most buyers can use the shorter figures.
- Urgency. A duly substantiated urgency allows 15 days for tenders in an open procedure, and 15 days for requests and 10 for tenders in a restricted or competitive procedure with negotiation. This is not the extreme urgency that allows no notice at all (below).
- By agreement. Where national law allows it, a sub-central buyer, meaning any buyer that is not central government, may agree the time for tenders with the selected candidates in a restricted or competitive procedure with negotiation, the same for each. Without agreement, it is at least 10 days.
When must a buyer give you more time?
Article 47 requires buyers to allow for the contract's complexity and the time needed to prepare tenders, and to give more time in three cases:
- if tenders can only be prepared after a site visit or an inspection of documents on the spot, the time limit must be longer than the minimum;
- if additional information you asked for in good time is not supplied at least six days before the deadline, or four in an urgent open or restricted procedure, the deadline must be extended;
- if the procurement documents change significantly, the deadline must be extended. Either extension must match the importance of the information or the change.
Buyers must also give free, unrestricted and full direct access to the procurement documents online from the day the notice is published. Where they cannot, for a reason the directive allows, the time for tenders is extended by five days, except in urgency.
How are the days counted?
The directive's recital 106 recalls that Regulation (EEC, Euratom) No 1182/71 on periods, dates and time limits applies to its time limits. Under that regulation:
- the day the notice or invitation is sent does not count; the period starts the next day;
- Saturdays, Sundays and public holidays count: these are calendar days, not working days;
- if the last day falls on a Saturday, Sunday or public holiday, the period ends at the end of the next working day.
The clock starts when the buyer sends the notice, not when it appears. The Publications Office of the EU publishes notices no later than five days after they are sent, so from the day you first see a notice on TED you may have up to five days less than the minimum. See the tenders closing this week for deadlines about to pass.
When can a buyer award a contract without a notice?
Only in the cases listed in Article 32, the negotiated procedure without prior publication. In short: when an open or restricted procedure drew no suitable tenders or requests; when only one company can do the work and there is no reasonable alternative; in extreme urgency caused by events the buyer could not foresee and did not cause; for a few kinds of supplies, such as products made purely for research; for a service contract after a design contest; and for repeat works or services within three years of the original contract, if its call for competition said so. With no notice, there is nothing to bid for unless you are the company concerned.
How do utilities' procedures differ?
Buyers in water, energy, transport and postal services follow Directive 2014/25/EU. They may choose the open, restricted or negotiated procedure with prior call for competition, the competitive dialogue or the innovation partnership, with no conditions on the choice. The open procedure follows the same figures, with a periodic indicative notice in place of the PIN. In the restricted and negotiated procedures, requests to participate get at least 30 days as a general rule, and never less than 15. The time for tenders may be agreed with the selected candidates, the same for each; without agreement, it is at least 10 days from the invitation to tender.
What does this mean for planning a bid?
In a two-stage procedure the first deadline is the request to participate, judged on selection information: have turnover figures, references and certificates ready before the notice appears. On any notice, the procedure and the deadlines are among the first things to check (how to read a TED notice). Browse what is open now in the tender directory.
Questions and answers
What is the minimum time limit in an open procedure?
35 days from the day the contract notice is sent, or 30 if the buyer accepts electronic tenders; as little as 15 after a prior information notice or in a substantiated urgency.
What are the minimum time limits in a restricted procedure?
30 days for requests to participate from the day the contract notice is sent, then 30 days for tenders from the day the invitation is sent, or 25 with electronic tenders.
Are the time limits in calendar days?
Yes. Weekends and public holidays count, the day the notice is sent does not, and a period ending on a Saturday, Sunday or public holiday runs to the end of the next working day.
Do these time limits apply in the UK?
No. The UK sets its own minimum tendering periods in section 54 of the Procurement Act 2023.
- Directive 2014/24/EU on public procurement: Article 1 (scope), Article 2 (definitions), Article 22 (electronic means), Article 26 (choice of procedures), Articles 27 to 32 (the procedures and their time limits), Article 47 (setting time limits), Article 51 (publication of notices), Article 53 (electronic availability of documents), Article 90 (transposition) and recital 106 (calculation of time limits), checked 5 November 2026: https://eur-lex.europa.eu/eli/dir/2014/24/oj
- Directive 2014/25/EU on procurement by entities operating in the water, energy, transport and postal services sectors: Article 44 (choice of procedures), Article 45 (open procedure), Article 46 (restricted procedure) and Article 47 (negotiated procedure with prior call for competition), checked 5 November 2026: https://eur-lex.europa.eu/eli/dir/2014/25/oj
- Regulation (EEC, Euratom) No 1182/71 determining the rules applicable to periods, dates and time limits: Article 3, checked 5 November 2026: https://eur-lex.europa.eu/eli/reg/1971/1182/oj
- Procurement Act 2023, section 54 (time limits), checked 5 November 2026: https://www.legislation.gov.uk/ukpga/2023/54/section/54